1. Building Control Authority (BCA)
2. Fire Safety Shelter Department (FSSD)
3. Housing Development Board (HDB)
4. National Environment Agency (NEA)
c. To design,calculate and endorse on Main Structural framing elements of Roof
d. To purchase plans from Relevant Plans from BCA and FSSD for submission purpose
3.1 To dismantle Existing Canopy and Footings
3.2 To hack off Existing Poles and Lights
3.3 To excavate and cave out roots for New RC Footings
3.4 To remove Existing Gutter and rainwater downpipes (RWDPs)
4.1 To cast RC Footings (RC Stumps) to receive new timber support
4.2 To supply waterproofing membrane
5.1 To erect Main Framing to support roof using 6-8mm thick Galvanized MS hollow sections
5.3 To cast New gutter and Aluminum Flashing with RWDPs
6.1 To erect false ceiling panel using Calcium Silicate Boards
6.2 To paint the ceiling